Maintenance, repair and site support

Facades, tanks, flare tips, and the ropes to reach them.

Facade panel replacement, tank refurbishment to API 653, flare-tip and derrick top-module change-outs, blasting and painting, bolt tensioning, heat treatment of pressure vessels and underwater maintenance, usually from the same ropes used for the inspection.

What is replaced and repaired How to engage Global Remote

Two technicians in a suspended yellow work cradle replacing glazing units on the sloping glass facade of an atrium.
Technical glazing remedial work on an atrium facade, carried out from a suspended cradle rather than a full scaffold.
What is replaced and repaired

Structures, skins and the things bolted to them.

The technicians are multi-skilled, so one mobilisation covers the survey, the remedial work and the reinstatement, with both halves done by one team.

Facades and glazing
Complete facade repair, aluminium composite panel replacement, facade retrofits, technical glazing installation, sealant application, substrate repair and reinforcing, integrated lighting installation and mega-format multimedia installation. On the Address Downtown Hotel in Dubai this was aluminium composite panel replacement as part of the hotel's remedial works.
Tanks
Tank refurbishment in accordance with API 653, AWWA and other national and international repair standards, alongside the inspection and testing. Sphere maintenance and inspection programmes, and the commissioning and decommissioning of ammonia storage tanks.
Flares, derricks and stacks
Flare-tip and top-module derrick replacement, flare guide rails and rollers, aircraft warning lights and re-wiring, derrick maintenance, repair and assembly, flare-tip to splash-zone maintenance, heli-deck remedial repairs, and stack and chimney work.
Steel and coatings
Blasting and painting, marine-standard coating and sealant application, steel renewals and bolt tensioning, remedial steel fabrication, piping composite repair systems, cathodic protection maintenance and repair, insulation works and industrial cleaning.
Underwater
Installation of clamps and bracings, underwater painting, block placing, geotextile laying, sheet-pile remedials, bolting and torquing, spool installation, marine growth removal, high-pressure jetting and steel structure repair, by certified divers.
Fit-out and installation
Structural component fabrication and installation, electrical fittings and wiring, mechanical and engineering support, HVAC ducting, telecommunications towers and systems, height-safety systems design and installation, and demolition and decommissioning.

Ammonia Tank Decommissioning and Commissioning

Periodically, refrigerated anhydrous liquid ammonia storage tanks must be inspected internally for integrity checks. This is a complex task which requires an appropriate level of competence and experience of ammonia storage tank design and operations. Some operators have only one single ammonia tank without spare capacity. This creates an additional pressure in terms of project managing the shutdown, decommissioning and inspection of the tank as well as reducing the total downtime since the production impact is highly costly.

Global Remote understands these challenges very well and we develop a comprehensive decommissioning inspection and repair plan. We offer a complete package from Decom, Inspect, Repair & Commission combined with advance NDT Inspection and using Rope Access techniques (cost effective alternative to traditional access methods, such as scaffolding or mobile elevated working platform) during tank inspection we minimise the downtime and reduce the out of production time for anhydrous liquid ammonia storage tanks.

Our work methodology includes:

  • Detailed job risk assessment
  • Decommissioning and inspection HAZOP study
  • Planning activities based on existing site condition
  • List of equipment and materials required
  • Inspection Procedure
  • Tank building location and specification
  • Emptying the tank
  • Key process parameters
  • Tank valve isolation for heating purpose
  • Inerting of system and purging with nitrogen
  • Gas sampling
  • Manway opening sequence
  • Danger of asphyxiant gas
  • Purging the tank with air
  • Readiness for confined entry
  • Non Destructive Inspection (VT, PT, MT, MFL, HT, RT etc)
  • Tank Floor & Foundation Inspection
  • Tank Repairs
  • Commissioning
Technicians in orange coveralls and hard hats fitting heating elements and insulation around a large welded pipe spool on site.
Heating elements and insulation set for a post-weld cycle. The weldment is heated, soaked and cooled to controlled temperatures.
Its own discipline

Heat treatment, and why the code asks for it.

Welding codes make heat treatment mandatory on certain materials, including carbon steels, stainless and high-alloy steels and work-hardened steels, and on certain wall thicknesses. Heat treatment reduces or redistributes the residual stress that welding introduces, by heating, soaking and cooling the weldment to controlled temperatures.

Pre-heating
Reduces the temperature difference between weld metal and parent metal as a molten weld cools, which minimises the tendency to crack during and after welding.
Post-weld heat treatment
By electrical resistance or by furnace or internal firing with high-velocity fuel burners. Three benefits: stress relaxation, tempering, and hydrogen removal.
Normalising
Improves the mechanical properties of steel. Tensile strength and impact value improve, giving better resistance to brittle fracture. For mild steel the temperature is around 900°C, roughly 50°C above the upper critical point.
Solution heat treatment
Certain austenitic stainless steels change structure between 500°C and 800°C in ways that damage corrosion resistance, and weld decay follows. Raising the material to 1000°C to 1150°C and cooling it rapidly gives immunity from decay.
Refractory dry out
Every furnace has refractory insulation installed, and it has to be dried out by heating the surface gradually to the manufacturer's procedure.
How to engage Global Remote

Into a window, or into your own crew.

Two commercial shapes, and they are genuinely different decisions. The first buys an outcome inside a date range; the second buys certified people who work under your supervision.

Into a shutdown or turnaround window

Planning, management and delivery are in house. Engineers visit the site weeks or months before the shutdown to begin pre-planning, then organise resources, logistics and manpower in advance so the critical path holds.

The scope covers mechanical services, chemical and industrial cleaning, industrial high-grade coating, insulation renewal, catalyst removal and reloading, and the provision of industrial rope access, complying with API, AWS, ASNT, BGAS, NACE, CSWIP and PCN.

The engineers on that work hold API 510 for pressure vessels, API 570 for piping and API 653 for storage tanks, with AWS certified welding inspectors, NACE certified painting inspectors, ASNT certified NDT technicians and IRATA-approved rope access.

Seconded into your own team

Skilled engineering and inspection staff for short-term or long-term hire, at short notice, with overseas recruitment for a project where needed. Teams also work as subcontractors to third-party agencies.

Disciplines include inspection engineers, construction and fabrication engineers, NDT, plant inspectors, painting and welding inspectors, hazardous materials specialists, QA/QC engineers and expeditors, auditors, calibration specialists and machine operators. Many are additionally trained in rope access, hazardous materials or confined-space work.

Based in India, and mobilised across the Indian subcontinent and the Middle East, including Qatar, the United Arab Emirates, Kuwait, Bahrain, Oman and Saudi Arabia.

Share the window

Six projects, in four lines each.

Facade replacement in Dubai, Horton spheres for Reliance, four flare tips inside a short shutdown, marine loading arms for a Total and Hindustan Petroleum joint venture, post-weld heat treatment for a repeat client, and cracked glazing on a Bahrain atrium.

Read the projects

Before any of it, someone has to get to the asset. That is where this starts.

Access without a shutdown